PROCESS BQUIPMENT AND INSTALLATION PAGE 1
PROJECT: West Coast Basis
DATE PREPARED: 16 OCT 1998 PREPARED BY: DEM PROJECT DATABASE: RIC
======----------------======================--===========------------------====
I REFERENCE NO: 107 HORIZ CATEGORY/TYPE: HT /HORIZ-DRUM
USER EQUIPMENT TAG_: ESTIMATED COST: USD 9600
ITEM
SHE4L MAT'L A 515 CAPACITY 660.00 GALLONS
DIAMETER 4. 00 FEET LENGTH 7.00 FEET
DESIGN TEMP. 650.00 DEG F DESIGN PRESS 15.00 PSIG
APPLICATION CONT THICKNESS 0.31 INCHES
TOTAL WEIGHT 2400 LBS
INSTALLATION
: INSTALLATION : DIRECT MAT'L: DIRECT FIELD LABOR :TOTAL DIRECT :
ACCOUNT USD MAN-HOURS USD USD ··
EQUIPMENT 9600 33 2763 12363
PIPING 0 0 0 0
CIVIL,SITEWORK 0 0 0 0
STEELWORK 0 0 0 0
INSTRUMENTATION 0 0 0 0
ELECTRICAL 0 0 0 0
INSULATI_ON 0 0 0 0
PAINTING 0 0 0 0
: TOTAL DIRECT COST: 9600 33 2763 12363
I I
CHEVRON MAKES NO WARRANTY
IMPLIED OR EXPRESSED, AS TO
ESTIMATES PROVIDED HEREIN.
CHEVRON STRONGLY SUGGESTS THAT
THE CITY OF SANTA CLARITA SHOULD
MAKE IT'S OWN DETERMINATION AS TO
THE SCOPE OF WORK NECESSARY TO
ACCOMPLISH THE GOAL SET FORTH AND
THE COST OF SUCH WORK.