P. 7
with the General Development Plan and shall.be submitted to County for
approval, which said approval shall not be unreasonably denied. No such
project shall be commenced by Society's own forces or contracts awarded
. prior to County approval of such plans and specifications.
6.03 · Society shall commence construction of the above-described
improvements within a reasonable time, including facilities for sewage and
telephone service, gas, water, el_ectrici ty and all applicable utility ·
·-
meters, following County's posting of the construction site with a notice of.
. .
non-responsibility, and shall. diligently prosecute and complete same.
6.04 Prior to the construction of the required security fencing,
as indicated in Exhibit A, Society shall adhere to the hours of operation
_designated by the Director.
6. 05 Closure of said property to public use by Society during said
construction shall, at the sole discretion of the Society, be limited (as to
area and time) to the extent required for the safety and convenience of the
public and their use and enjoyment of said fac{lities.
6.06 No modification of said final plans and specifications or of
said improvements, including landscaping, shall be made by Society without
prior approval therefor of the Director.
6.07 Society agrees that County may have on the site at any time
during the construction period an inspector who shall have the right of
. .
access to said property· and construction work. Society shall, at the
commencement of the construction work, notify the Director in writing of the
identity, place of business, and telephone mnnber of Society's representa-
tive. Said representative shall be Society's prime-consultant for the
inspector of County.