Cost Estimate Summary
                    Historic Pioneer Refinary
                    City of Santa Clarita



                    Task                                                   Low Cost   Most Likely Cost   High Cost    Sour.ce
                    Preliminary Seismic Engineering                     $       1,000  $       1,200  $        3,000  Consultant verbal estimate
                    Seismic Analysis of Existing Structures             $      13,800  $      24,800  $       46,800  Consultant verbal estimate
                    Prepare Scope for Rebuilt Structures                $         200  $         700  $        2,700  Consultant verbal estimate
                    Replicate  Acid Treating Tank and Wash Tank platform   $      300  $         800  $        1,700  Internal Calculations
                    Design Ramps,  Parking Lot,  Entrance (ADA)         $         500  $       1,500  $        2,800  Internal Calculations
                                                                                                                                                 1
                    Purchase Placards                                   $       5,000  $       6,000  $        8,000  Sign Company verbal estimates
                    Interior Fencing                                    $       4,000  $       4,200  $        4,800  Verbal Quote from fencing company
                    Construction                                        $      24,000  $      29,000  $       48,000  Consultant verbal estimate
                    Restore Structures                                                                                Included
                    Repair Foundations                                                                                Included Above
                                                                                                                                                 1
                    Corrosion  Cleansing                                $       8,500  $       9,400  $       11,800  Verbal Estimate from Contractor
                    Realign Still w/crane                               $       1,300  $       2,500  $        8,500  Internal Calculations
                                                                                                                                                 I
                    Brick Restoration                                   $      15,000  $      20,000  $       30,000  contractor proposal
                    Rebuild Missing Structures                          $      59,000  $      96,200  $      104,200  Internal Calculations      I
                    Install Trail                                        $        -    $         -    $              Assumed Volunteer Work      I  I
                    Install Placards                                    $         300  $         600  $        2,000  Internal Calculations
                                                                                                                                                 I
                    Total                                               $     132,900  $     196,900  $      274,300                             I
                    Chevron Commitment                                  $      15,000  $      15,000  $       15,000
                    Remaining Expenditures                              $     117,900  $     181,900  $      259,300

                    CHEVRON MAKES NO WARRANTY,  IMPLED OR
                    EXPRESSED, AS TO THE ESTIMATES PROVIDED
                    HEREIN.  CHEVRON STRONGLY SUGGESTS THAT
                    THE CITY OF SANTA CLARITA SHOULD MAKE ITS
                    OWN DETERMINATION AS TO THE SCOPE of
                    WORK NECESSARY TO ACCOMPLISH THE GOALS
                    SET FORTH AND THE COST OF SUCH WORK