Page 694 - scvhs19901997minutes
P. 694
u
,
,
Mogul 1629/Tender/Rolling Stock Restoration
N. Harris
9/8/97
Equipment Restoration Task Cost Time to Canplete
Site Canvas Awning $5,000 1 month
u Locomotive Bearings/Axles $250 1 week
Prepare pads
Jack-Up/Set Down 1 week
fl Clean Bearings $150 1 month
$100
(Concurrent)
Lubricate
u
Reassemble A/C $250 6 months
Reassemble Parts $500 4 months
Install Piping $250 4 months
Fabricate Jacket
Sheet Metal Fabrication $5000* 2 months
Install Sheet Metal $5000* 1 month
Restore Cab
Replace Corroded Metal $500 2 months
Install on Locomotive $250 1 week
Replace Ceiling/Windows $1300* 3 months
n Install Flooring $100 1 week
I· i Complete Cab Electrical $150 1 month
t.J
Locomotive Lights (Headlight is restored)
l .
I l Purchase Running Lights $500 1 week
\ __ .] Purchase Numbers $150 1 week
.. Install Lights $250 2 weeks
i '
I • Air Compressor(Blow Whistle/Operate Tools}
l '
Purchase $2500 1 day
Install(Elect./Plumb.) $250 2 weeks
I .
I
L, Paint Locomotive
Sand Blast $1000* 1 week
Purchase Paint $2500 1 day
Apply Paint $2500* 1 month
Number/Letter $500* 1 month
Sub Totals: $2i<=t 50 28.8 months