COUNTY OF LOS ANGELES Page 6/7
DEPARTMENT OF PUBLIC WORKS
LAND DEVELOPMENT DIVISION - ROAD
TRACT NO. 60922 /Amend.) TENTATIVE MAP DATED 11-16-2016
EXHIBIT "A" MAP DATED 11-16-2016
i) Request the Street Lighting Section to commence annexation and
levy of assessment proceedings.
ii) Provide business/property owner's name(s), mailing address(es),
site address, Assessor Parcel Number(s), and Parcel Boundaries in
either Microstation or Auto GADD format of territory to be
developed to the Street Lighting Section.
iii) Submit a map of the proposed project, including any roadways
conditioned for street lights that are outside the proposed project
area, to Street Lighting Section. Contact the Street Lighting
Section for map requirements and with any questions at
(626) 300-4 726.
c. Note that the annexation and assessment balloting process takes
approximately twelve months or more to complete once the above
information is received and approved. Therefore, untimely compliance
with the above will result in a delay in receiving approval of the street
lighting plans or in filing the final subdivision map for recordation.
Information on the annexation and the assessment balloting process can
be obtained by contacting Street Lighting Section at (626) 300-4726.
d. For acceptance of street light transfer billing, the area must be annexed
into the Lighting District and all street lights in the development, or the
current phase of the development, must be constructed according to
Public Works apprbved plans. The contractor shall submit one complete
set of "as-built" plans.
e. The Lighting District can assume responsibility for the operation and
maintenance of the street lights in the project, or the current phase of the
project, as of July 1st of any given year provided the above conditions are
met and the street lights have been energized and the developer has
requested a transfer of billing at least by January 1st of the previous year.
The transfer of billing could be delayed one or more years if the above
conditions are not met.
37. Underground all new utility lines to the satisfaction of Public Works and Southern
California Edison. Please contact Construction Division at (626) 458-3129 for
new location of any above ground utility structure in the parkway.
38. Provide and install street name signs prior to occupancy of buildings.