Project Background
The Skyline Ranch project site occupies approximately 2,173 acres in unincorporated Los Angeles County. As
shown on Figure 3, Approved TTM, the Approved Project includes development on approximately 622 acres
of the 2,173-acre site with 1,260 single-family residential lots, an approximately 11.6-acre elementary school
site, about 12 acres of public parkland to be dedicated to the Los Angeles County Department of Parks and
Recreation, and about 6.2 acres of private parkland. Nearly three-quarters of the site (the northern 1,551
acres) would remain undeveloped, with approximately 1,355 acres dedicated or designated as natural open
space through establishment of the proposed Skyline Ranch Conservation Area (SRCA). Approximately 166
acres of undeveloped land in the northern portion of the site would remain undeveloped and designated as
Non-development/Continuing Use Area. Also, within the northern portion of the site, approximately 22
acres would be preserved as a Mitigation Exchange Area for 22 acres of preserve area within adjacent
recorded Tract 46018 that would be disturbed due to the construction of Skyline Ranch Road. These three
areas would preserve approximately 80 percent of the land in the County's Cruzan Mesa Vernal Pools SEA.
No development associated with the Skyline Ranch Project would occur in the SEA areas.
A proposed trail would extend the existing Mint Canyon Trail from Vasquez Canyon Road to the Plum
Canyon Fire Road along an existing dirt path and southwesterly toward a lookout point. The proposed trail
easement would run approximately 2.2 miles within portions of the SRCA and Nondevelopment/
Continuing Use Area. The Approved Project would include two miles of hiking trails, one mile
of paseo trails, and eight miles of bike lanes.
Modified Project Description
The Modified Project includes minor technical changes to the approved Skyline Ranch project. Figure 4,
Approved TTM vs. Proposed Concept Plan, shows the proposed conceptual site plan, which includes the
modifications described below. Figure 5, Development Footprint Comparison, shows an overlay of the Modified
and Approved Projects. The Modified Project would have a smaller development footprint within the
footprint of the Approved Project. In total, the site would be divided into seventeen planning areas (PAs),
designated PA A through Q, one park sites, seven recreation center sites, and one school site (see Figure 6,
Modified Conceptual Lot Plan).
• Realignment of Skyline Ranch Road. The Modified Project would shift Skyline Ranch Road west of
the original alignment. All residential development would be east of the roadway rather than divided by
the original alignment. Skyline Ranch Road would maintain its designation as a secondary highway and is
proposed to have roundabouts at intersections within the project boundaries. The two access points of
Skyline Ranch Road at Plum Canyon Road (to the west) and Sierra Highway (to the southeast) would not
change.
• Reduction of residential development and inclusion of age-qualified housing. Residential
development would be reduced from 1,260 to 1,220 lots (40 fewer units). The homes along the western
edge of the property would be removed and/or shifted east of the realigned Skyline Ranch Road, and
284 units of age-qualified housing with a recreation center would be provided in the northern portion of
the planned community in PAs G through K.
• Modifications to housing product types. A broader range of lot sizes and housing types is now
proposed, including smaller, more affordable homes for first-time buyers or move-down buyers that were
not included in the original plan. There would be a total of six product types and 1,220 dwelling units.
• Relocation of park and recreation sites. The park sites proposed under the Approved Project would
be relocated and combined into one large park adjacent to the school, as shown on Figure 4, Approved
TTM vs. Proposed Concept Plan. Approximately 16.9 acres of public parkland to be dedicated to the Los
Angeles County Department of Parks and Recreation would be relocated to be accessible without
crossing streets — in particular without crossing Skyline Ranch Road. Seven recreation centers would be
located within the Skyline Ranch community and connected by a multi-purpose trail system. Additionally,
the Modified Project includes 2.7 acres of private parkland (a recreation center for age-qualified housing).
• Addition of multipurpose trails. The Modified Project would include 10.75 miles of pedestrian
connections, which includes 3 miles of hiking trails, a 2.2-mile trail easement, 3.3 miles of paseo trails,
and 2.3 miles of multipurpose trails (see Figure 7, Open Space and Trails Map).
• Extension of bike lanes. Bike lanes within the Skyline Ranch community would extend from 8 miles to
9.8 miles under the Modified Project.
A comprehensive comparison of the Approved and Modified Projects' land use development and housing
product types is provided in Tables 2 and 3.
Additionally, the Modified Project would reduce the number of basins from 13 to 12, but the 4 water tanks at
the northern portion of the developable area under the Approved Project would remain. Overall, the
Modified Project would have a reduced development footprint within the Approved Project's development
footprint (see Table 2 and Figure 5, Development Footprint Comparison). Compared to the Approved Project,
grading quantities would decrease by approximately 18 and 19 percent for cut and fill quantities, respectively.
The cut and fill quantities would decrease to approximately 17.1 million cubic yards (cy) cut and 16.9 million
cy fill.